Answer First
Primary Text
The grantee shall undertake the electrification of all unenergized barangays in the Municipality of Ibaan, Province of Batangas, within the radius of five kilometers (5 km.) from its existing lines within five (5) years and the remaining unenergized barangays in the said municipality within fifteen (15) years from the effectivity of this Act.
Should there be applications for connections within an unenergized barangay from more than one hundred (100) households, the grantee is obligated to accelerate the electrification and to provide electric service within a year of application.
Use With Care
Definitions and exceptions often appear before or after this text.
Court decisions may interpret, limit, or apply this provision.
Confirm amendment, repeal, effectivity, and official publication.