Pre-bid Conference. - At least one pre-bid conference shall be conducted for each procurement, unless otherwise provided in the IRR. Subject to the approval of the BAC, a pre-bid conference may also be conducted upon the written request of any prospective bidder.
The Pre-bid conference(s) shall be held within a reasonable period before the deadline for receipt of the bids to allow prospective bidders to adequately prepare their bids, which shall be specified in the IRR.
ARTICLE VIII
RECEIPT AND OPENING OF BIDS