Failure to Enter into Contract and Post Performance Security. - If, for justifiable causes, the bidder with the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid fails, refuses or is otherwise unable to enter into contract with the Procuring Entity, or if the bidder fails to post the required performance security within the period stipulated in the Bidding Documents, the BAC shall disqualify the said bidder and shall undertake post-qualification for the next-ranked Lowest Calculated Bid or Highest Rated Bid. This procedure shall be repeated until an award is made. However, if no award is possible, the contract shall be subjected to a new bidding.
In the case of a failure to post the required performance security, the bid security shall be forfeited without prejudice to the imposition of sanctions prescribed under Article XXIII.
Use With Care
Definitions and exceptions often appear before or after this text.
Court decisions may interpret, limit, or apply this provision.
Confirm amendment, repeal, effectivity, and official publication.