Warranty. - (a) For the procurement of Goods, in order to assure that manufacturing defects shall be corrected by the supplier, manufacturer, or distributor, as the case maybe, for a specific time after performance of the contract, a warranty shall be required from the contract awardee for such period of time as may be provided in the IRR, the obligation for which shall be covered by either retention money in the amount equivalent to a percentage of every progress payment, or a special bank guarantee equivalent to a percentage of the total contract price, to be provided in the IRR. The said amounts shall only be released after the lapse of the warranty period, provided that the Goods supplied are free from defects and all the conditions imposed under the contract have been fully met.
b. For the procurement of infrastructure projects, the contractor shall assume full responsibility for the contract work from the time project construction commenced up to a reasonable period as defined in the IRR taking into consideration the scale and coverage of the project from its final acceptance by the government and shall be held responsible for any damage or construction or works except those occasioned by force majeure.
The contractor shall be fully responsible for the safety, protection, security, and convenience of his personnel, third parties, and the public large, as well as the works, equipment, installation and the like to be affected by his construction work and shall be required to put up a warranty security in the form of cash, bank guarantee, letter of credit, Government Service Insurance System bond, or callable surety bond.
The contractor shall undertake the repair works, at his own expense, of any defect or damage to the infrastructure projects on account of the use of materials of inferior quality within ninety (90) days from the time the Head of the Procuring Entity has issued an order to undertake repair. In case of failure or refusal to comply with this mandate, the governments shall undertake such repair works and shall be entitle to full reimbursement of expenses incurred therein upon demand.
Any contractor who fails to comply with the preceding paragraphs shall suffer perpetual disqualification from participating in any public bidding and his property or properties shall be subject to attachment or garnishment proceedings to recover the costs. All payables of government in his favor shall be offset to recover the costs.
ARTICLE XX
THE GOVERNMENT PROCUREMENT POLICY BOARD
Use With Care
Definitions and exceptions often appear before or after this text.
Court decisions may interpret, limit, or apply this provision.
Confirm amendment, repeal, effectivity, and official publication.