Existing Facilities within the Protected Area. Existing facilities within the protected area shall be inventoried and assessed by the PAMB in accordance with the objectives of this Act. Within thirty (30) days from the effectivity of this Act, unless extended by the PAMB, all commercial facilities existing within the boundaries of the protected area with a total capitalization exceeding One hundred thousand pesos (P100,000.00) shall submit to the PAMB through the Protected Area Superintendent the following information:
(a) Environmental Impact Assessment and/or Environmental Management Plan;
(b) Environmental Compliance Certificate, if any; and
(c) Developmental Plan, if any.
Failure to submit the required information shall constitute a violation of this Act. Based on its submission, the PAMB, with the assistance of the DENR shall assess such facility and its future plan and operation vis-a-vis the objectives of this Act. The PAMB may prescribe conditions for the operation of the facility to ensure that it does not contradict protected area management objectives. If any of such conditions are violated, a fine of Five thousand pesos (P5,000.00) for every day of violation shall be imposed. If the fine reaches the total amount of Five hundred thousand pesos (P500,000.00), regardless of duration; the PAMB, through the Protected Area Superintendent and deputizing other government entities, shall cause the cessation and demolition of the facility at the cost of its owners.
The removal of existing facilities which provide basic services and amenities to the public shall require the concurrence of the LGU consistent with the responsibility of the local government to its constituents.
Existing facilities allowed to remain within the protected area may be charged a reasonable fee, subject to DENR approval pursuant to Section 10(f) of the NIPAS Act by the PAMB based on the extent of its impact on the environment and biodiversity.
Use With Care
Definitions and exceptions often appear before or after this text.
Court decisions may interpret, limit, or apply this provision.
Confirm amendment, repeal, effectivity, and official publication.