Answer First
Primary Text
NPC Stranded Debt and Contract Cost Recovery. Stranded debt of NPC shall refer to any unpaid financial obligations of NPC.
Stranded contract costs of NPC shall refer to the excess of the contracted cost of electricity under eligible IPP contracts of NPC over the actual selling price of the contracted energy output of such contracts in the market. Such contracts shall have been approved by the ERB as of December 31, 2000.
The national government shall directly assume a portion of the financial obligations of NPC in an amount not to exceed Two hundred billion pesos (P200,000,000,000,00)
The ERC shall verify the reasonable amounts and determine the manner and duration for the full recovery of stranded debt and stranded contract costs as defined herein: Provided, That the duration for such recovery shall not be shorter than fifteen (15) years nor longer than twenty-five (25) years. The ERC shall, at the end of the first year of the implementation of stranded cost recovery and every year thereafter, conducts a review to determine whether there is under-recovery or over-recovery and adjust (tune-up) the level of stranded cost recovery charge accordingly. Any amount to be included for stranded cost recovery shall be reflected as a separate item in the consumer billing statement.
Use With Care
Definitions and exceptions often appear before or after this text.
Court decisions may interpret, limit, or apply this provision.
Confirm amendment, repeal, effectivity, and official publication.