Distribution Utilities Stranded Contract Costs Recovery. Stranded contract costs of distribution utilities shall refer to the excess of the contracted cost of electricity under eligible contracts of such utilities over the actual selling price of such contracts in the market. Such contracts shall have been approved by the ERB as of December 31, 2000.
A distribution utility shall recover stranded contract costs: Provided, however, That such costs of the IPPs of distribution utilities are subject to review by ERC in order to determine fairness and reasonableness in relation to the average price of land-based IPP projects entered into by NPC at the time they were contracted. The ERC shall take into consideration all factors that affect the total cost of NPC IPP generation projects, including direct or indirect subsidies or incentives provided by the Government.
Within one (1) year from the start of open access, any distribution utility that seeks recovery of stranded contract costs shall file with the ERC notice of such intent together with an estimate of such obligations, including the present value thereof and such other supporting data as may be required by the ERC. Any distribution utility that does not file within the date specified shall not be eligible for such recovery.
Any distribution utility which seeks to recover stranded cost shall have a duty to mitigate its potential stranded contract costs by making reasonable best efforts to:
(a) reduce the costs of its existing contracts with IPPs to a level not exceeding the average buying price of other land-based electric power generators; and
(b) submit to an annual earnings review by the ERC and use its earnings above its authorized rate of return to reduce the book value of contracts until the end of the stranded cost recovery period.
Other mitigating measures which are reasonably known and generally accepted within the electric power industry shall be utilized. The ERC shall not require the distribution utility to take a loss to reduce stranded contract costs or divest assets, unless the divestiture is imposed as a penalty as provided herein.
The relevant distribution utility shall submit to the ERC quarterly reports showing the amount of stranded costs recovered and the balance remaining to be recovered.
Within three (3) months from the submission of the application for stranded cost recovery by the relevant distribution utilities, the ERC shall verify the reasonable amounts and determine the manner and duration for the full recovery of stranded contract costs as defined herein: Provided, That the duration for such recovery shall not be shorter than fifteen (15) years nor longer than twenty-five (25) years. Any amount to be included for stranded cost recovery shall be reflected as a separate item in the consumer billing statement.
The ERC shall, at the end of the first year of the implementation of stranded cost recovery and every year thereafter, conduct a review to determine whether there is under-recovery or over recovery and adjust (true-up) the level of stranded cost recovery charge accordingly. In case of an over-recovery, the ERC shall ensure that any excess amount shall be remitted to the Special Trust Fund created under Section 34 hereof. A separate account shall be created for these amounts which shall be held in trust for any future claims of distribution utilities for stranded cost recovery. At the end of the stranded cost recovery period, any remaining amount in this account shall be used to reduce the electricity rates to the end-users.
Use With Care
Definitions and exceptions often appear before or after this text.
Court decisions may interpret, limit, or apply this provision.
Confirm amendment, repeal, effectivity, and official publication.